Thanks Teddi. Good to hear from someone who is there. Way better than looking at pictures.

 

Interesting you mention the power. I wondered about that myself. They only put in a 10 meg substation and they only signed a contract with Hydro One for about 5 megs so far. The 2500 HP hoist draws a little under 2 megs. That leaves 8 megs for everything else. There is no power shortage right now in NWO so the actual line from Ear Falls would be the bottleneck.    I hope it does not cross any WFN traditional land.

 

Any sign of Labine on site?

 

Keep the info flowing Teddi