Ok,,, so there are some capex cost overuns partially related to upgrades.

$15 million. Well, that is not the end of the world to me, but I am somewhat confused by the fact that here we are in Feb. still running at the "batch" level.

I had assumed that the commisioning was referring to running on a continuous loop.

It seems to me that there is a lot of commisioning left to do. This is not what I was expecting to hear at this point.

I think it is time for a corporate update but I suspect that management won't want to do that right now until they can mix it in with some very good news such as the fact that they are now producing 5n or some such similar good news.

I am feeling a little "in the dark" right now. Also,,,, does anyone know the cash position right now?