Services, utilities, infrastructure and civil engineering work have now been 100% completed and approximately 80% of the main process equipment is on site, which is ahead of the original schedule. Initial Commercial production of 4N to 6N high purity alumina is expected to begin in Q1 2013 with the production capacity gradually increasing to 3 tonnes per day by mid-2013. As part of the HPA plant design, part of the equipment has already been provisioned to a capacity of 5 tonnes per day. Orbite anticipates the installation in H2 2013 of the additional equipment necessary to achieve production of 5 tonnes per day by the end of 2013.