CGG Jiama PreFeas NR Cover.pdf. The mine life is estimated to be 31 years based on the Mineral Reserve. The Project at full production has a planned average mining production rate of 13.6 Mtpa ROM ore to 2039. tage two is expected to be completed by 2014 copper production expected to reach approximately 176,400,000 pounds up from its 2012 level of 25,820,417 pounds.

  • The Company expects to complete the Jiama Mine's Phase II Independent Feasibility Study and to release an updated NI43-101 compliant report in the second quarter of 2013.
  • Jiama is expected to reach its planned full capacity of 40,000 tpd of ore.
  • The Company plans to drill approximately 30,000 meters at the Jiama Mine during 2013.

    China National Gold targets RMB 100-bln revenue in 2015!